81fac49933 docs(status): mark #27 badges complete 2026-01-10 18:47:34 -07:00
Test User
253c8888aa docs(status): mark #24 and #26 complete 2026-01-10 18:44:49 -07:00
Test User
94cb7493db docs(status): mark CONTRIBUTING.md guide complete 2026-01-10 18:22:37 -07:00
Test User
e28d20b856 docs: remove community issues from phase structure
Reverted changes to issues not created by frankbria:
- #44, #54, #64, #65 removed from phase assignments
- Restored original issue titles on GitHub
- Removed phase labels from community issues
- Updated open issue counts (40 → 36)
2026-01-10 15:09:17 -07:00
Test User
bada82e4e2 docs(status): update IMPLEMENTATION_STATUS.md with phased structure
- Update test counts (75 -> 276) and all test file details
- Convert from Week-based to Phase-based structure (Phases 1-6)
- Add all GitHub issues organized by phase and priority
- Update version history with v0.9.0-v0.9.8 changes
- Add summary statistics and open issues by priority
- Collapse closed issues into expandable section
2026-01-10 15:02:08 -07:00
frankbria
d9960e4683 docs: synchronize implementation documentation with codebase (2025-12-31)
Update all base directory documentation to accurately reflect current codebase state:

- IMPLEMENTATION_PLAN.md: Correct CI/CD status (operational), update test counts (75 actual),
  clarify week completion status (1-2 + partial 5 complete)
- IMPLEMENTATION_STATUS.md: Add verification dates, detailed test breakdowns, updated remaining
  work estimates, recent improvements section
- STATUS.md: Update from 35 to 75 tests, add integration test details, include lib/ modules
- PHASE1_COMPLETION.md & PHASE2_COMPLETION.md: Add historical milestone notes

Key corrections:
- CI/CD pipeline IS operational (.github/workflows/test.yml)
- install.sh DOES copy lib/ directory (verified lines 78, 91, 148)
- 75 tests accurately reported (15 rate + 20 exit + 20 loop + 20 edge)
- Week 5 partially complete (edge cases done, features not implemented)
- Weeks 3-4 and 6 not started (accurate status vs. optimistic claims)

All documentation now synchronized with codebase as of 2025-12-31.
2025-12-31 17:14:09 -07:00
frankbria
d7171e29a4 docs: Update implementation plan with actual progress
Updates IMPLEMENTATION_PLAN.md to reflect completed work:
- Week 1-2 fully complete (test infrastructure + unit tests)
- Phase 1-2 enhancements complete (response analyzer + circuit breaker)
- 75 tests written and passing (35 unit + 40 integration)
- ~60% code coverage achieved

Created IMPLEMENTATION_STATUS.md for detailed tracking:
- Comprehensive breakdown of completed vs remaining work
- Test coverage analysis
- Priority recommendations for remaining work
- Success metrics dashboard

Key achievements beyond original plan:
 Response analyzer (lib/response_analyzer.sh)
 Circuit breaker (lib/circuit_breaker.sh)
 40 integration tests (test_loop_execution + test_edge_cases)
 Comprehensive Phase 1-2 documentation (2,300+ lines)

Remaining work: Weeks 3-6 (installation, tmux, features, E2E tests)